Sy No. 34/1 & 35/1, Halasahalli, Tippasandra, Sarjapura, Anekal, Bengaluru Urban, Karnataka - 560087

Total Plots
73
Total Area
5.07 Acres
Handover
31 Mar 2026

RERA progress

Stage 4 of 4 · Handover
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(completed)
  4. Handover(current stage)

RERA Approved

17 Jun 2025

PRM/KA/RERA/1251/308/PR/170625/007837

Est. Handover as per RERA

31 Mar 2026

Configurations & unit mix

9.14 X 12.19M18about 1,200 sq ft each
9.14 X 15.24M17about 1,499 sq ft each
Odd Site2about 883 sq ft each
10.05 X 15.24M3about 1,647 sq ft each
Odd Site27about 1,471 sq ft each
6.10 X 12.19 M6about 800 sq ft each

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete100%

Quarter
Q4 2025-26
Filed on
10 Apr 2026
Reports on file
2

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/308/PR/170625/007837)

Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/308/PR/170625/007837
Registered as
Prime Acres Samasti
Promoter
PRIME ACRES PRoJECTS
Acknowledgement no.
ACK/KA/RERA/1251/308/PR/210425/009156
Status on the register
Ongoing
Stage
Ready (per RERA completion date)
Work stage
100% complete, Q4 2025-26 report filed 10 Apr 2026
RERA approved on
17 Jun 2025
Proposed completion
31 Mar 2026
Land area
5.07 acres (20,510 sq m)
Plots (this registration)
73
Plan approved by
BDA - Bangalore Development Authority
Approved plan no.
BDA/TPM/PRL-19/2023-24/3041/2023-24
Plan approval date
26 Mar 2024
Land use
Residential

Dates on the register

Completion filed with RERA
31 Mar 2026 (Karnataka RERA)
Latest construction report
100% complete, Q4 2025-26, filed 10 Apr 2026 (promoter's report to RERA)

This date has passed. Our copy of the register has no handover dates, so it can't tell you whether homes were delivered. This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Approval Layout Order / Technical Sanction Letter
  • Approved Layout Plan/Demarcation Plan
  • NOC for Water
  • Form-4 certificate (Chartered Accountant)
  • Form-6 certificate (Structural Engineer)

Location

About Prime Acres Samasti

Development of 73 Plots, 3 Parks and other public utilities

Developer
PRIME ACRES PRoJECTS
Project Type
Plotted Development
Type
Plotted Development
Status
Ready (per RERA completion date)
Total Land
5.07 Acres
Total Plots
73
Handover Date
31 Mar 2026
RERA No.
PRM/KA/RERA/1251/308/PR/170625/007837
Location
Anekal, Bangalore

About the developer

PRIME ACRES PRoJECTS

Promoter on the register
PRIME ACRES PRoJECTS
Projects on the register
1
Registering since
2025
Complaints on the promoter
0, as shown on this registration

Prime Acres Samasti: questions answered

Where is Prime Acres Samasti located?

The Karnataka RERA register places Prime Acres Samasti in Anekal, Bengaluru Urban.

What is the RERA number of Prime Acres Samasti?

The Karnataka RERA registration number of Prime Acres Samasti is PRM/KA/RERA/1251/308/PR/170625/007837, approved on 17 Jun 2025.

Who is the promoter of Prime Acres Samasti?

The promoter filed on the Karnataka RERA register is PRIME ACRES PRoJECTS.

What completion date was filed for Prime Acres Samasti?

The completion date filed on the register was 31 Mar 2026. Check the register for any extension.

How big is Prime Acres Samasti?

The register lists Prime Acres Samasti with 73 plots and about 5.07 acres of land.

What is the latest construction progress of Prime Acres Samasti?

The quarterly report for Q4 2025-26, filed on 10 Apr 2026, shows construction 100% complete.

Where does this information about Prime Acres Samasti come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.