Registered Project
Ready (per RERA completion date)Metropolis Fair Oaks II Extn
Sy.No.243/2 and Sy.No.245, Sarjapura Village Sarjapura Hobli Anekal Taluk 560011
- Handover
- 31 Dec 2025
RERA progress
Stage 4 of 4 · Handover- RERA applied(completed)
- RERA approved(completed)
- Under construction(completed)
- Handover(current stage)
RERA Approved
4 Dec 2021
PRM/KA/RERA/1251/308/PR/211204/004571
Est. Handover as per RERA
31 Dec 2025
Latest quarterly report on the register
Construction progress
Construction complete100%
- Quarter
- Q3 2025-26
- Filed on
- 20 Jan 2026
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/308/PR/211204/004571)
Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/308/PR/211204/004571
- Registered as
- METROPOLIS FAIR OAKS II EXTN
- Acknowledgement no.
- ACK/KA/RERA/1251/308/PR/210327/004858
- Status on the register
- New Project Launch
- Stage
- Ready (per RERA completion date)
- Work stage
- 100% complete, Q3 2025-26 report filed 20 Jan 2026 (over 9 months old)
- RERA approved on
- 4 Dec 2021
- Proposed completion
- 31 Dec 2025
- Plan approved by
- BMRDA - Bangalore Metropolitan Region Development Authority
Dates on the register
- Completion filed with RERA
- 31 Dec 2025 (Karnataka RERA)
- Latest construction report
- 100% complete, Q3 2025-26, filed 20 Jan 2026 (over 9 months old) (promoter's report to RERA)
This date has passed. Our copy of the register has no handover dates, so it can't tell you whether homes were delivered. This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Approved Building/Plotting Plan
- Approved Layout Plan
- Approved Section Of Building/Infrastructure Plan of Plotting
- Area Development Plan Of Project Area
- Certificate from Registered Engineer indicating the structural safety of the building (for Apartments)
- Conversion Certificate under Sec 95 of the KLR Act 1961
- Existing Layout Plan
- Existing Section Plan and Specification
- Lift Authorities
- Proforma of Agreement for Sale
- Project Specification
- Transfer of development rights certificate
- Utilisation certificate
- Form-6 certificate (Structural Engineer)
Location
About Metropolis Fair Oaks II Extn
Plotted development
- Type
- Plotted Development
- Status
- Ready (per RERA completion date)
- Handover Date
- 31 Dec 2025
- RERA No.
- PRM/KA/RERA/1251/308/PR/211204/004571
- Location
- Anekal, Bangalore
Metropolis Fair Oaks II Extn: questions answered
Where is Metropolis Fair Oaks II Extn located?
The Karnataka RERA register places Metropolis Fair Oaks II Extn in Anekal, Bengaluru Urban.
What is the RERA number of Metropolis Fair Oaks II Extn?
The Karnataka RERA registration number of Metropolis Fair Oaks II Extn is PRM/KA/RERA/1251/308/PR/211204/004571, approved on 4 Dec 2021.
What completion date was filed for Metropolis Fair Oaks II Extn?
The completion date filed on the register was 31 Dec 2025. Check the register for any extension.
What is the latest construction progress of Metropolis Fair Oaks II Extn?
The quarterly report for Q3 2025-26, filed on 20 Jan 2026, shows construction 100% complete.
Where does this information about Metropolis Fair Oaks II Extn come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.