Skip to main content
PropSarathi

Registered Project

Ready (per RERA completion date)

MAHIDHARA PROJECTS PRIVATE LIMITED

Mahidhara Harmony

Mahidhara Harmony, Sy. No.125/1, 125/2, 126/2, 126/3,126/4,131/6 Muthanallur Village, Sarjapura Hobli, Anekal Taluk, Bengaluru, Anekal, Bengaluru Urban, Karnataka - 560099

Total Units
146
Floors
2
Towers
8
Total Area
9.79 Acres
Handover
10 Sept 2026

RERA progress

Stage 4 of 4 · Handover
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(completed)
  4. Handover(current stage)

RERA Approved

21 Nov 2022

PRM/KA/RERA/1251/308/PR/211122/005487

Est. Handover as per RERA

10 Sep 2026

Developer target: 10 Sept 2026

Configurations & unit mix

FLATS -3 BHK119
FLATS -4 BHK27

The promoter's RERA report, Q2 2026-27, filed 15 Oct 2026, by its own types and totals, which don't line up with the rows above. Types listed more than once are added together: 3 BHK 45 of 119 available; 4 BHK 9 of 27 available.

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete98%

Quarter
Q2 2026-27
Filed on
15 Oct 2026
Units booked
91 of 146
Units available
55
Reports on file
4

Amenities

  • Electricity
  • CCTV Surveillance
  • Club House
  • Outdoor Sports facility
  • Indoor Sports facility
  • Swimming Pool
  • Gym
  • Parks
  • Power Backup
  • Water and Sanitation

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/308/PR/211122/005487)

Complaints on the register: 1 recorded on this project; 1 on the promoter's record, as shown on this registration

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/308/PR/211122/005487
Registered as
Mahidhara Harmony
Promoter
MAHIDHARA PROJECTS PRIVATE LIMITED
Acknowledgement no.
ACK/KA/RERA/1251/308/PR/220822/006268
Status on the register
New Project Launch
Stage
Ready (per RERA completion date)
Work stage
98% complete, Q2 2026-27 report filed 15 Oct 2026
Sales status
Ongoing Sales (per RERA QPR Q2 2026-27, as of 15 Oct 2026)
RERA approved on
21 Nov 2022
Proposed completion
10 Sept 2026
Land area
9.79 acres (39,608 sq m)
Towers (this registration)
8
Floors (this registration)
2
Units (this registration)
146
Plan approved by
Local Planing Authority
Plan approval date
3 Jan 2022
Land use
Residential

Dates on the register

Completion filed with RERA
10 Sep 2026 (Karnataka RERA)
Latest construction report
98% complete, Q2 2026-27, filed 15 Oct 2026 (promoter's report to RERA)

This date has passed. Our copy of the register has no handover dates, so it can't tell you whether homes were delivered. The latest report above says 98%. This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Commencement Certificate
  • Electricity Permission Letter
  • Water Permission Letter
  • Approved Layout Plan
  • Approved Building/Plotting Plan
  • Existing Section Plan and Specification
  • Sectional Drawing of the apartments
  • Project Specifications
  • Approved Section Of Building/Infrastructure Plan of Plotting
  • Area Development Plan Of Project Area
  • Certificate from Registered Engineer indicating the structural safety of the building
  • Proforma of Agreement for Sale
  • ESCOM/Electricity
  • KWSSB/Water
  • Approval/NOC under section 109 of KLR Act 1961
  • Approval/NOC under section 14 of the KTCP Act
  • Fire Force Department
  • Airport Authority of India
  • KSPCB
  • SEIAA

Location

About Mahidhara Harmony

Construction of villa with an extend of 9 Acres 31.5 Guntas of land consists of 146 villas situated at Mahidhara Harmony, Sy. No.Sy. No.125/1, 125/2, 126/2, 126/3,126/4,131/6 Muthanallur Village, Sarjapura Hobli, Anekal Taluk, Bengaluru - 560099.

Developer
MAHIDHARA PROJECTS PRIVATE LIMITED
Project Type
Residential/Group Housing
Type
Villa
Status
Ready (per RERA completion date)
Total Land
9.79 Acres
No. of Towers
8
No. of Floors
2
Total Units
146
Handover Date
10 Sept 2026
RERA No.
PRM/KA/RERA/1251/308/PR/211122/005487
Location
Anekal, Bangalore

About the developer

MAHIDHARA PROJECTS PRIVATE LIMITED

Promoter on the register
MAHIDHARA PROJECTS PRIVATE LIMITED
Projects on the register
2
Registering since
2022
Complaints on the promoter
1, as shown on this registration

Mahidhara Harmony: questions answered

Where is Mahidhara Harmony located?

The Karnataka RERA register places Mahidhara Harmony in Anekal, Bengaluru Urban.

What is the RERA number of Mahidhara Harmony?

The Karnataka RERA registration number of Mahidhara Harmony is PRM/KA/RERA/1251/308/PR/211122/005487, approved on 21 Nov 2022.

Who is the promoter of Mahidhara Harmony?

The promoter filed on the Karnataka RERA register is MAHIDHARA PROJECTS PRIVATE LIMITED.

What completion date was filed for Mahidhara Harmony?

The completion date filed on the register was 10 Sept 2026. Check the register for any extension.

How big is Mahidhara Harmony?

The register lists Mahidhara Harmony with 146 units, 8 towers and about 9.79 acres of land.

What is the latest construction progress of Mahidhara Harmony?

The quarterly report for Q2 2026-27, filed on 15 Oct 2026, shows construction 98% complete and 91 of 146 units booked.

Where does this information about Mahidhara Harmony come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.