Skip to main content
PropSarathi

Registered Project

Under Construction

KBR INFRATECH LIMITED

KBR Estates

SY NO.S: 16 & 17/3 OF RAJAPURA VILLAGE, JIGANI HOBLI, Anekal, Bengaluru Urban, Karnataka - 560105

Total Plots
99
Total Area
7.1 Acres
Handover
31 Mar 2030

RERA progress

Stage 3 of 4 · Under construction
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(current stage)
  4. Handover(upcoming)

RERA Approved

13 Jun 2025

PRM/KA/RERA/1251/308/PR/130625/007826

Est. Handover as per RERA

31 Mar 2030

Configurations & unit mix

10.68M X 12.19M14about 1,402 sq ft each
10.68M X 15.24M23about 1,752 sq ft each
Odd-sized plots54about 1,680 sq ft each
9.14M X 15.24M8about 1,499 sq ft each

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete90%

Quarter
Q2 2026-27
Filed on
15 Oct 2026
Reports on file
4

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/308/PR/130625/007826)

Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/308/PR/130625/007826
Registered as
KBR ESTATES
Promoter
KBR INFRATECH LIMITED
Acknowledgement no.
ACK/KA/RERA/1251/308/PR/220325/009064
Status on the register
Ongoing
Stage
Under Construction
Work stage
90% complete, Q2 2026-27 report filed 15 Oct 2026
RERA approved on
13 Jun 2025
Proposed completion
31 Mar 2030
Land area
7.1 acres (28,732 sq m)
Plots (this registration)
99
Plan approved by
Anekal Planning Authority
Approved plan no.
AAYOPRAA/LAO/13/2024-25
Plan approval date
20 Oct 2024
Land use
Residential

Dates on the register

Completion filed with RERA
31 Mar 2030 (Karnataka RERA)
Latest construction report
90% complete, Q2 2026-27, filed 15 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Approval Layout Order / Technical Sanction Letter
  • Approved Layout Plan/Demarcation Plan
  • Declaration (Form B)
  • Advocate Search Report
  • NOC from ESCOMs
  • NOC for Water
  • KSPCB (If Applicable)
  • SEIAA (If Applicable)
  • Form-4 certificate (Chartered Accountant)
  • Form-6 certificate (Structural Engineer)

Location

About KBR Estates

Developer
KBR INFRATECH LIMITED
Type
Plotted Development
Status
Under Construction
Total Land
7.1 Acres
Total Plots
99
Handover Date
31 Mar 2030
RERA No.
PRM/KA/RERA/1251/308/PR/130625/007826
Location
Anekal, Bangalore

About the developer

KBR INFRATECH LIMITED

Promoter on the register
KBR INFRATECH LIMITED
Projects on the register
1
Registering since
2025
Complaints on the promoter
0, as shown on this registration

KBR Estates: questions answered

Where is KBR Estates located?

The Karnataka RERA register places KBR Estates in Anekal, Bengaluru Urban.

What is the RERA number of KBR Estates?

The Karnataka RERA registration number of KBR Estates is PRM/KA/RERA/1251/308/PR/130625/007826, approved on 13 Jun 2025.

Who is the promoter of KBR Estates?

The promoter filed on the Karnataka RERA register is KBR INFRATECH LIMITED.

When is KBR Estates expected to be completed?

The proposed completion date filed on the register is 31 Mar 2030.

How big is KBR Estates?

The register lists KBR Estates with 99 plots and about 7.1 acres of land.

What is the latest construction progress of KBR Estates?

The quarterly report for Q2 2026-27, filed on 15 Oct 2026, shows construction 90% complete.

Where does this information about KBR Estates come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.