Registered Project
Ready (per RERA completion date)Green Field Homes
Sy no. 97/1, Site No. 284 and 285, Kachanayakanahalli Village, Hennagara Post, Jigani Hobli, Anekal Taluk, Bengaluru, Karnataka – 560105, Anekal, Bengaluru Urban, Karnataka - 560105
- Total Units
- 15
- Floors
- 3
- Towers
- 2
- Total Area
- 0.48 Acres
- Handover
- 27 Mar 2025
RERA progress
Stage 4 of 4 · Handover- RERA applied(completed)
- RERA approved(completed)
- Under construction(completed)
- Handover(current stage)
RERA Approved
2 Sep 2023
PRM/KA/RERA/1251/308/PR/020923/006226
Est. Handover as per RERA
27 Mar 2025
Configurations & unit mix
| VILLA | 1 |
|---|---|
| VILLA | 14 |
The register doesn't list prices, so none are shown here.
Amenities
- Electricity
- CCTV Surveillance
- Outdoor Sports facility
- Swimming Pool
- Gym
- Parks
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/308/PR/020923/006226)
Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/308/PR/020923/006226
- Registered as
- GREEN FIELD HOMES
- Acknowledgement no.
- ACK/KA/RERA/1251/308/PR/060623/007170
- Status on the register
- Ongoing
- Stage
- Ready (per RERA completion date)
- RERA approved on
- 2 Sept 2023
- Proposed completion
- 27 Mar 2025
- Land area
- 0.48 acres (1,956 sq m)
- Towers (this registration)
- 2
- Floors (this registration)
- 3
- Units (this registration)
- 15
- Plan approved by
- BMRDA - Bangalore Metropolitan Region Development Authority
- Approved plan no.
- APA/CC/709/2022-23
- Plan approval date
- 28 Mar 2023
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 27 Mar 2025 (Karnataka RERA)
This date has passed. Our copy of the register has no handover dates, so it can't tell you whether homes were delivered. This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Commencement Certificate
- Electricity Permission Letter
- Approved Layout Plan
- Approved Building/Plotting Plan
- Existing Layout Plan
- Existing Section Plan and Specification
- Sectional Drawing of the apartments
- Project Specifications
- Approved Section Of Building/Infrastructure Plan of Plotting
- Area Development Plan Of Project Area
- Certificate from Registered Engineer indicating the structural safety of the building
- Change of Land Use
- Proforma of Agreement for Sale
- Proforma of Allotment Letter
- Brochure
- ESCOM/Electricity
- Approval/NOC under section 109 of KLR Act 1961
- Approval/NOC under section 14 of the KTCP Act
- Fire Force Department
- Airport Authority of India
Location
About Green Field Homes
Fully loaded Residential complex of 15 villas
- Project Type
- Residential/Group Housing
- Type
- Villa
- Status
- Ready (per RERA completion date)
- Total Land
- 0.48 Acres
- No. of Towers
- 2
- No. of Floors
- 3
- Total Units
- 15
- Handover Date
- 27 Mar 2025
- RERA No.
- PRM/KA/RERA/1251/308/PR/020923/006226
- Location
- Anekal, Bangalore
Green Field Homes: questions answered
Where is Green Field Homes located?
The Karnataka RERA register places Green Field Homes in Anekal, Bengaluru Urban.
What is the RERA number of Green Field Homes?
The Karnataka RERA registration number of Green Field Homes is PRM/KA/RERA/1251/308/PR/020923/006226, approved on 2 Sept 2023.
What completion date was filed for Green Field Homes?
The completion date filed on the register was 27 Mar 2025. Check the register for any extension.
How big is Green Field Homes?
The register lists Green Field Homes with 15 units, 2 towers and about 0.48 acres of land.
Where does this information about Green Field Homes come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.