Registered Project
Ready (per RERA completion date)Green City
Sy No.110/1B, Lingapura Village Kasaba Hobli, Anekal, Bengaluru Urban, Karnataka - 560105
- Total Plots
- 31
- Total Area
- 1.77 Acres
- Handover
- 30 Jun 2023
RERA progress
Stage 4 of 4 · Handover- RERA applied(completed)
- RERA approved(completed)
- Under construction(completed)
- Handover(current stage)
RERA Approved
6 Apr 2023
PRM/KA/RERA/1251/308/PR/060423/005836
Est. Handover as per RERA
30 Jun 2023
Configurations & unit mix
| SITES MEASURING 9.14 * 12.19 MTR | 10 |
|---|---|
| ODD SITES | 21 |
The register doesn't list prices, so none are shown here.
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/308/PR/060423/005836)
Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/308/PR/060423/005836
- Registered as
- GREEN CITY
- Acknowledgement no.
- ACK/KA/RERA/1251/308/PR/161022/006446
- Status on the register
- Ongoing
- Stage
- Ready (per RERA completion date)
- RERA approved on
- 6 Apr 2023
- Proposed completion
- 30 Jun 2023
- Land area
- 1.77 acres (7,183 sq m)
- Plots (this registration)
- 31
- Plan approved by
- Local Planing Authority
- Approved plan no.
- LAO:74:2021-22
- Plan approval date
- 23 Oct 2021
Dates on the register
- Completion filed with RERA
- 30 Jun 2023 (Karnataka RERA)
This date has passed. Our copy of the register has no handover dates, so it can't tell you whether homes were delivered. This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Electricity Permission Letter
- Water Permission Letter
- Approved Layout Plan
- Existing Layout Plan
- Existing Section Plan and Specification
Location
About Green City
Plotted Development
- Project Type
- Plotted Development
- Type
- Plotted Development
- Status
- Ready (per RERA completion date)
- Total Land
- 1.77 Acres
- Total Plots
- 31
- Handover Date
- 30 Jun 2023
- RERA No.
- PRM/KA/RERA/1251/308/PR/060423/005836
- Location
- Anekal, Bangalore
Green City: questions answered
Where is Green City located?
The Karnataka RERA register places Green City in Anekal, Bengaluru Urban.
What is the RERA number of Green City?
The Karnataka RERA registration number of Green City is PRM/KA/RERA/1251/308/PR/060423/005836, approved on 6 Apr 2023.
What completion date was filed for Green City?
The completion date filed on the register was 30 Jun 2023. Check the register for any extension.
How big is Green City?
The register lists Green City with 31 plots and about 1.77 acres of land.
Where does this information about Green City come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.