Skip to main content
PropSarathi

Registered Project

Under Construction

Ranke Infra LLP

GR Swara

GR Swara, Situated at Sy No. 48/1P, 49/2, 49/5, 49/6, 49/7, Choodasandra Village, Sarjapura Hobli, Anekal, Bengaluru Urban, Karnataka - 560099

Total Units
57
Floors
4
Towers
8
Total Area
2.91 Acres
Handover
31 Jan 2029

RERA progress

Stage 3 of 4 · Under construction
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(current stage)
  4. Handover(upcoming)

RERA Approved

2 Jun 2025

PRM/KA/RERA/1251/308/PR/020625/007803

Est. Handover as per RERA

31 Jan 2029

Configurations & unit mix

Row Houses57

The promoter's RERA report, Q2 2026-27, filed 18 Oct 2026, by its own types and totals, which don't line up with the rows above. Types listed more than once are added together: COMMERCIAL 0 of 1 available; 4 BHK + Fam + MP 54 of 57 available.

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete43%

Quarter
Q2 2026-27
Filed on
18 Oct 2026
Units booked
4 of 58
Units available
54
Reports on file
4

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/308/PR/020625/007803)

Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/308/PR/020625/007803
Registered as
GR Swara
Promoter
Ranke Infra LLP
Acknowledgement no.
ACK/KA/RERA/1251/308/PR/210325/009059
Status on the register
New Project Launch
Stage
Under Construction
Work stage
43% complete, Q2 2026-27 report filed 18 Oct 2026
Sales status
Ongoing Sales (per RERA QPR Q2 2026-27, as of 18 Oct 2026)
RERA approved on
2 Jun 2025
Proposed completion
31 Jan 2029
Land area
2.91 acres (11,760 sq m)
Towers (this registration)
8
Floors (this registration)
4
Units (this registration)
57
Plan approved by
BDA - Bangalore Development Authority
Approved plan no.
45/2024-25
Plan approval date
7 Jan 2025
Land use
Residential

Dates on the register

Completion filed with RERA
31 Jan 2029 (Karnataka RERA)
Latest construction report
43% complete, Q2 2026-27, filed 18 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Commencement Certificate
  • Approved Building Plan
  • Sectional Drawing of the apartments
  • Certificate from Registered Engineer indicating the structural safety of the building
  • Project Specifications
  • Brochure
  • Relinquishment Deed
  • Proforma of Agreement for Sale
  • Proforma of Allotment Letter
  • Advocate Search Report
  • ESCOM/Electricity
  • KWSSB/Water
  • KSPCB
  • SEIAA
  • Fire Force Department
  • Airport Authority of India
  • BSNL
  • Lift Authorities
  • BMRCL
  • NOC in case of building proposals abutting to neighbouring properties

Location

About GR Swara

Sy No. 48/1P, 49/2, 49/5, 49/6, 49/7 Situated at Choodasandra Village, Sarjapura Hobli, Anekal Taluk

Developer
Ranke Infra LLP
Project Type
Residential/Group Housing
Type
Row Houses
Status
Under Construction
Total Land
2.91 Acres
No. of Towers
8
No. of Floors
4
Total Units
57
Handover Date
31 Jan 2029
RERA No.
PRM/KA/RERA/1251/308/PR/020625/007803
Location
Anekal, Bangalore

About the developer

Ranke Infra LLP

Promoter on the register
Ranke Infra LLP
Projects on the register
1
Registering since
2025
Complaints on the promoter
0, as shown on this registration

GR Swara: questions answered

Where is GR Swara located?

The Karnataka RERA register places GR Swara in Anekal, Bengaluru Urban.

What is the RERA number of GR Swara?

The Karnataka RERA registration number of GR Swara is PRM/KA/RERA/1251/308/PR/020625/007803, approved on 2 Jun 2025.

Who is the promoter of GR Swara?

The promoter filed on the Karnataka RERA register is Ranke Infra LLP.

When is GR Swara expected to be completed?

The proposed completion date filed on the register is 31 Jan 2029.

How big is GR Swara?

The register lists GR Swara with 57 units, 8 towers and about 2.91 acres of land.

What is the latest construction progress of GR Swara?

The quarterly report for Q2 2026-27, filed on 18 Oct 2026, shows construction 43% complete and 4 of 58 units booked.

Where does this information about GR Swara come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.