Total Units
270
Floors
13
Towers
3
Total Area
3.09 Acres
Handover
28 Feb 2031

RERA progress

Stage 2 of 4 · RERA approved
  1. RERA applied(completed)
  2. RERA approved(current stage)
  3. Under construction(upcoming)
  4. Handover(upcoming)

RERA Approved

17 Apr 2026

PRM/KA/RERA/1251/308/PR/170426/008589

Est. Handover as per RERA

28 Feb 2031

Configurations & unit mix

3 BHK207197 of 207988 – 1,148 sq ft
2 BHK6353 of 63701 – 807 sq ft

Available from the promoter's RERA report, Q2 2026-27, filed 8 Oct 2026.

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete18%

Quarter
Q2 2026-27
Filed on
8 Oct 2026
Units booked
20 of 270
Units available
250
Reports on file
2

Amenities

  • Electricity
  • CCTV Surveillance
  • Club House
  • Community Hall
  • Indoor Sports facility
  • Swimming Pool
  • Gym
  • Parks
  • Power Backup
  • Water and Sanitation

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/308/PR/170426/008589)

Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/308/PR/170426/008589
Registered as
GMC CONFLUENCE
Promoter
Grihamithra Confra Private Limited
Acknowledgement no.
ACK/KA/RERA/1251/308/PR/130326/010096
Status on the register
New Project Launch
Stage
New Launch
Work stage
18% complete, Q2 2026-27 report filed 8 Oct 2026
Sales status
Ongoing Sales (per RERA QPR Q2 2026-27, as of 8 Oct 2026)
RERA approved on
17 Apr 2026
Proposed completion
28 Feb 2031
Land area
3.09 acres (12,520 sq m)
Towers (this registration)
3
Floors (this registration)
13
Units (this registration)
270
Plan approved by
Satellite Town Ring Road Planning Authority
Approved plan no.
STRRPA/TP/CC/197/2025-26
Plan approval date
6 Feb 2026
Land use
Residential

Dates on the register

Completion filed with RERA
28 Feb 2031 (Karnataka RERA)
Latest construction report
18% complete, Q2 2026-27, filed 8 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Commencement Certificate
  • Approved Building Plan
  • Sectional Drawing of the apartments
  • Certificate from Registered Engineer indicating the structural safety of the building
  • Project Specifications
  • Relinquishment Deed
  • Proforma of Agreement for Sale
  • Proforma of Allotment Letter
  • Advocate Search Report
  • ESCOM/Electricity
  • KWSSB/Water
  • KSPCB
  • SEIAA
  • Fire Force Department
  • Airport Authority of India
  • Lift Authorities
  • BMRCL
  • NOC in case of building proposals abutting to neighbouring properties
  • Bangalore Urban Arts Commission
  • Inspector Of Factories Controller Of Explosives Railways

Location

About GMC Confluence

Construction of Residential Building with 270 Units at Sy No. 7/3, Billapura Village, Sarjapura Hobli, Anekal Taluk, Bengaluru Urban, Karnataka 562125

Developer
Grihamithra Confra Private Limited
Project Type
Residential/Group Housing
Type
Apartment
Status
New Launch
Total Land
3.09 Acres
No. of Towers
3
No. of Floors
13
Total Units
270
Handover Date
28 Feb 2031
RERA No.
PRM/KA/RERA/1251/308/PR/170426/008589
Location
Anekal, Bangalore

About the developer

Grihamithra Confra Private Limited

Promoter on the register
Grihamithra Confra Private Limited
Projects on the register
1
Registering since
2026
Complaints on the promoter
0, as shown on this registration

GMC Confluence: questions answered

Where is GMC Confluence located?

The Karnataka RERA register places GMC Confluence in Anekal, Bengaluru Urban.

What is the RERA number of GMC Confluence?

The Karnataka RERA registration number of GMC Confluence is PRM/KA/RERA/1251/308/PR/170426/008589, approved on 17 Apr 2026.

Who is the promoter of GMC Confluence?

The promoter filed on the Karnataka RERA register is Grihamithra Confra Private Limited.

When is GMC Confluence expected to be completed?

The proposed completion date filed on the register is 28 Feb 2031.

How big is GMC Confluence?

The register lists GMC Confluence with 270 units, 3 towers and about 3.09 acres of land.

What is the latest construction progress of GMC Confluence?

The quarterly report for Q2 2026-27, filed on 8 Oct 2026, shows construction 18% complete and 20 of 270 units booked.

Where does this information about GMC Confluence come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.