Registered Project
Under ConstructionSahara Grand
SY. NO. 77/1, 77/6(P) & 78/1, CHIKKANAGAMANGALA VILLAGE, SARJAPURA HOBLI, Anekal, Bengaluru Urban, Karnataka - 560099
- Total Units
- 365
- Floors
- 4
- Towers
- 1
- Total Area
- 3.15 Acres
- Handover
- 31 Jan 2029
RERA progress
Stage 3 of 4 · Under construction- RERA applied(completed)
- RERA approved(completed)
- Under construction(current stage)
- Handover(upcoming)
RERA Approved
16 Aug 2024
PRM/KA/RERA/1251/308/PR/160824/006972
Est. Handover as per RERA
31 Jan 2029
Configurations & unit mix
| 2 BHK | 99 | 10 of 99 | 603 – 774 sq ft |
|---|---|---|---|
| 4 BHK | 33 | 916 – 1,039 sq ft | |
| 3 BHK | 233 | 609 – 984 sq ft |
Available from the promoter's RERA report, Q2 2026-27, filed 13 Oct 2026.
The promoter's RERA report, Q2 2026-27, filed 13 Oct 2026, by its own types and totals, which don't line up with the rows above. Types listed more than once are added together: 3 BHK 131 of 231 available; 4 BHK 19 of 31 available.
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete66%
- Quarter
- Q2 2026-27
- Filed on
- 13 Oct 2026
- Units booked
- 201 of 361
- Units available
- 160
- Reports on file
- 4
Amenities
- Electricity
- CCTV Surveillance
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/308/PR/160824/006972)
Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/308/PR/160824/006972
- Registered as
- DS MAX SAHARA GRAND
- Acknowledgement no.
- ACK/KA/RERA/1251/308/PR/240524/008178
- Status on the register
- New Project Launch
- Stage
- Under Construction
- Work stage
- 66% complete, Q2 2026-27 report filed 13 Oct 2026
- Sales status
- Ongoing Sales (per RERA QPR Q2 2026-27, as of 13 Oct 2026)
- RERA approved on
- 16 Aug 2024
- Proposed completion
- 31 Jan 2029
- Land area
- 3.15 acres (12,747 sq m)
- Towers (this registration)
- 1
- Floors (this registration)
- 4
- Units (this registration)
- 365
- Plan approved by
- BDA - Bangalore Development Authority
- Approved plan no.
- 55/2023-24
- Plan approval date
- 23 Feb 2024
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 31 Jan 2029 (Karnataka RERA)
- Latest construction report
- 66% complete, Q2 2026-27, filed 13 Oct 2026 (promoter's report to RERA)
This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Commencement Certificate
- Electricity Permission Letter
- Water Permission Letter
- Approved Building/Plotting Plan
- Existing Section Plan and Specification
- Sectional Drawing of the apartments
- Project Specifications
- Approved Section Of Building/Infrastructure Plan of Plotting
- Advocate Search Report
- Any other document (Rights/Title/Interest/Name)
- Proforma of Agreement for Sale
- Proforma of Allotment Letter
- Declaration (Form B)
- ESCOM/Electricity
- KWSSB/Water
- Approval/NOC under section 109 of KLR Act 1961
- Approval/NOC under section 14 of the KTCP Act
- Fire Force Department
- Airport Authority of India
- KSPCB
Location
About Sahara Grand
Construction of Residential Apartment Comprises of 365 Flats of different dimensions
- Project Type
- Residential/Group Housing
- Type
- Apartment
- Status
- Under Construction
- Total Land
- 3.15 Acres
- No. of Towers
- 1
- No. of Floors
- 4
- Total Units
- 365
- Handover Date
- 31 Jan 2029
- RERA No.
- PRM/KA/RERA/1251/308/PR/160824/006972
- Location
- Anekal, Bangalore
Sahara Grand: questions answered
Where is Sahara Grand located?
The Karnataka RERA register places Sahara Grand in Anekal, Bengaluru Urban.
What is the RERA number of Sahara Grand?
The Karnataka RERA registration number of Sahara Grand is PRM/KA/RERA/1251/308/PR/160824/006972, approved on 16 Aug 2024.
When is Sahara Grand expected to be completed?
The proposed completion date filed on the register is 31 Jan 2029.
How big is Sahara Grand?
The register lists Sahara Grand with 365 units, 1 tower and about 3.15 acres of land.
What is the latest construction progress of Sahara Grand?
The quarterly report for Q2 2026-27, filed on 13 Oct 2026, shows construction 66% complete and 201 of 361 units booked.
Where does this information about Sahara Grand come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.