- Total Units
- 253
- Floors
- 8
- Towers
- 2
- Total Area
- 3.61 Acres
- Handover
- 31 Jul 2025
RERA progress
Stage 4 of 4 · Handover- RERA applied(completed)
- RERA approved(completed)
- Under construction(completed)
- Handover(current stage)
RERA Approved
30 Jan 2024
PRM/KA/RERA/1251/308/PR/300124/006588
Est. Handover as per RERA
31 Jul 2025
Configurations & unit mix
| BLOCK-2 | 152 |
|---|---|
| BLOCK-1 | 101 |
The register doesn't list prices, so none are shown here.
Amenities
- Electricity
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/308/PR/300124/006588)
Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/308/PR/300124/006588
- Registered as
- ARS Signaturehomes Phase-2
- Acknowledgement no.
- ACK/KA/RERA/1251/308/PR/291123/007631
- Status on the register
- Ongoing
- Stage
- Ready (per RERA completion date)
- RERA approved on
- 30 Jan 2024
- Proposed completion
- 31 Jul 2025
- Land area
- 3.61 acres (14,619 sq m)
- Towers (this registration)
- 2
- Floors (this registration)
- 8
- Units (this registration)
- 253
- Plan approved by
- Local Planing Authority
- Approved plan no.
- 371
- Plan approval date
- 21 Nov 2023
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 31 Jul 2025 (Karnataka RERA)
This date has passed. Our copy of the register has no handover dates, so it can't tell you whether homes were delivered. This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Electricity Permission Letter
- Water Permission Letter
- Approved Layout Plan
- Approved Building/Plotting Plan
- Existing Layout Plan
- Existing Section Plan and Specification
- Project Specifications
- Approved Section Of Building/Infrastructure Plan of Plotting
- Area Development Plan Of Project Area
- Certificate from Registered Engineer indicating the structural safety of the building
- Change of Land Use
- Conversion Certificate under section 95 of the KLR Act 1964
- Proforma of Agreement for Sale
- Proforma of Allotment Letter
- Brochure
- ESCOM/Electricity
- Approval/NOC under section 109 of KLR Act 1961
- Approval/NOC under section 14 of the KTCP Act
- Fire Force Department
- Airport Authority of India
Location
About ARS Signaturehomes Phase-2
RESIDENTIAL APARTMENT PROJECT CONSTRUCTING AT SOMPURA VILLAGE ANEKAL
- Project Type
- Residential/Group Housing
- Type
- Apartment
- Status
- Ready (per RERA completion date)
- Total Land
- 3.61 Acres
- No. of Towers
- 2
- No. of Floors
- 8
- Total Units
- 253
- Handover Date
- 31 Jul 2025
- RERA No.
- PRM/KA/RERA/1251/308/PR/300124/006588
- Location
- Anekal, Bangalore
ARS Signaturehomes Phase-2: questions answered
Where is ARS Signaturehomes located?
The Karnataka RERA register places ARS Signaturehomes in Anekal, Bengaluru Urban.
What is the RERA number of ARS Signaturehomes?
The Karnataka RERA registration number of ARS Signaturehomes is PRM/KA/RERA/1251/308/PR/300124/006588, approved on 30 Jan 2024.
What completion date was filed for ARS Signaturehomes?
The completion date filed on the register was 31 Jul 2025. Check the register for any extension.
How big is ARS Signaturehomes?
The register lists ARS Signaturehomes with 253 units, 2 towers and about 3.61 acres of land.
Where does this information about ARS Signaturehomes come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.