- 30 Sept 2026
RERA progress
Stage 4 of 4 · Handover- RERA applied(completed)
- RERA approved(completed)
- Under construction(completed)
- Handover(current stage)
RERA Approved
9 Nov 2022
PRM/KA/RERA/1251/308/PR/091122/005429
Est. Handover as per RERA
30 Sep 2026
Developer target: 30 Sept 2026
Configurations & unit mix
| Flats | 349 |
|---|
The promoter's RERA report, Q2 2026-27, filed 15 Oct 2026, by its own types and totals, which don't line up with the rows above. Types listed more than once are added together: 2 BHK 64 of 141 available; 3 BHK 81 of 208 available.
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete96%
- Quarter
- Q2 2026-27
- Filed on
- 15 Oct 2026
- Units booked
- 204 of 349
- Units available
- 145
- Reports on file
- 4
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Power Backup
- Water and Sanitation
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/308/PR/091122/005429)
Complaints on the register: 1 recorded on this project; 1 on the promoter's record, as shown on this registration
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/308/PR/091122/005429
- Registered as
- ALCHEMY ELIXIR
- Promoter
- ARATT CITY TOWERS LLP
- Acknowledgement no.
- ACK/KA/RERA/1251/308/PR/050922/006314
- Status on the register
- New Project Launch
- Stage
- Ready (per RERA completion date)
- Work stage
- 96% complete, Q2 2026-27 report filed 15 Oct 2026
- Sales status
- Ongoing Sales (per RERA QPR Q2 2026-27, as of 15 Oct 2026)
- RERA approved on
- 9 Nov 2022
- Proposed completion
- 30 Sept 2026
- Land area
- 3.99 acres (16,137 sq m)
- Towers (this registration)
- 2
- Floors (this registration)
- 12
- Units (this registration)
- 349
- Plan approved by
- BDA - Bangalore Development Authority
- Plan approval date
- 23 Jun 2022
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 30 Sep 2026 (Karnataka RERA)
- Latest construction report
- 96% complete, Q2 2026-27, filed 15 Oct 2026 (promoter's report to RERA)
This date has passed. Our copy of the register has no handover dates, so it can't tell you whether homes were delivered. The latest report above says 96%. This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Commencement Certificate
- Electricity Permission Letter
- Water Permission Letter
- Approved Layout Plan
- Approved Building/Plotting Plan
- Existing Layout Plan
- Existing Section Plan and Specification
- Sectional Drawing of the apartments
- Project Specifications
- Approved Section Of Building/Infrastructure Plan of Plotting
- Area Development Plan Of Project Area
- Certificate from Registered Engineer indicating the structural safety of the building
- Change of Land Use
- Conversion Certificate under section 95 of the KLR Act 1964
- Proforma of Agreement for Sale
- Proforma of Allotment Letter
- Brochure
- ESCOM/Electricity
- KWSSB/Water
- Approval/NOC under section 109 of KLR Act 1961
Location
About Alchemy Elixir
ALCHEMY ELIXIR IS A RESIDENTIAL
- Developer
- ARATT CITY TOWERS LLP
- Project Type
- Residential/Group Housing
- Type
- Apartment
- Status
- Ready (per RERA completion date)
- Total Land
- 3.99 Acres
- No. of Towers
- 2
- No. of Floors
- 12
- Total Units
- 349
- Handover Date
- 30 Sept 2026
- RERA No.
- PRM/KA/RERA/1251/308/PR/091122/005429
- Location
- Anekal, Bangalore
About the developer
ARATT CITY TOWERS LLP
- Promoter on the register
- ARATT CITY TOWERS LLP
- Projects on the register
- 2
- Registering since
- 2022
- Complaints on the promoter
- 1, as shown on this registration
Alchemy Elixir: questions answered
Where is Alchemy Elixir located?
The Karnataka RERA register places Alchemy Elixir in Anekal, Bengaluru Urban.
What is the RERA number of Alchemy Elixir?
The Karnataka RERA registration number of Alchemy Elixir is PRM/KA/RERA/1251/308/PR/091122/005429, approved on 9 Nov 2022.
Who is the promoter of Alchemy Elixir?
The promoter filed on the Karnataka RERA register is ARATT CITY TOWERS LLP.
What completion date was filed for Alchemy Elixir?
The completion date filed on the register was 30 Sept 2026. Check the register for any extension.
How big is Alchemy Elixir?
The register lists Alchemy Elixir with 349 units, 2 towers and about 3.99 acres of land.
What is the latest construction progress of Alchemy Elixir?
The quarterly report for Q2 2026-27, filed on 15 Oct 2026, shows construction 96% complete and 204 of 349 units booked.
Where does this information about Alchemy Elixir come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.