Registered Project
New LaunchSON INFRA ENTERPRISES
Aavya Homes
SY NO 138/3 AND 138/4 AT KAMMASANDRA VILLAGE, ATTIBELE HOBLI, Anekal, Bengaluru Urban, Karnataka - 560100
- Total Units
- 80
- Floors
- 3
- Towers
- 1
- Total Area
- 0.73 Acres
- Handover
- 31 Dec 2028
RERA progress
Stage 2 of 4 · RERA approved- RERA applied(completed)
- RERA approved(current stage)
- Under construction(upcoming)
- Handover(upcoming)
RERA Approved
20 Jan 2026
PRM/KA/RERA/1251/308/PR/200126/008411
Est. Handover as per RERA
31 Dec 2028
Configurations & unit mix
| 2 BHK | 28 | 25 of 28 | 646 – 754 sq ft |
|---|---|---|---|
| 3 BHK | 52 | 49 of 52 | 805 – 960 sq ft |
Available from the promoter's RERA report, Q4 2025-26, filed 15 Jul 2026.
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete70%
- Quarter
- Q4 2025-26
- Filed on
- 15 Jul 2026
- Units booked
- 6 of 80
- Units available
- 74
Amenities
- Electricity
- CCTV Surveillance
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/308/PR/200126/008411)
Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/308/PR/200126/008411
- Registered as
- AAVYA HOMES
- Promoter
- SON INFRA ENTERPRISES
- Acknowledgement no.
- ACK/KA/RERA/1251/308/PR/210725/009436
- Status on the register
- Ongoing
- Stage
- New Launch
- Work stage
- 70% complete, Q4 2025-26 report filed 15 Jul 2026
- Sales status
- Ongoing Sales (per RERA QPR Q4 2025-26, as of 15 Jul 2026)
- RERA approved on
- 20 Jan 2026
- Proposed completion
- 31 Dec 2028
- Land area
- 0.73 acres (2,968 sq m)
- Towers (this registration)
- 1
- Floors (this registration)
- 3
- Units (this registration)
- 80
- Plan approved by
- Anekal Planning Authority
- Approved plan no.
- APA/CC/04/2018-19
- Plan approval date
- 3 Mar 2025
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 31 Dec 2028 (Karnataka RERA)
- Latest construction report
- 70% complete, Q4 2025-26, filed 15 Jul 2026 (promoter's report to RERA)
This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Commencement Certificate
- Approved Building Plan
Location
About Aavya Homes
DEVELOPMENT OF RESIDENTIAL APARTMENT
- Developer
- SON INFRA ENTERPRISES
- Project Type
- Residential/Group Housing
- Type
- Apartment
- Status
- New Launch
- Total Land
- 0.73 Acres
- No. of Towers
- 1
- No. of Floors
- 3
- Total Units
- 80
- Handover Date
- 31 Dec 2028
- RERA No.
- PRM/KA/RERA/1251/308/PR/200126/008411
- Location
- Anekal, Bangalore
About the developer
SON INFRA ENTERPRISES
- Promoter on the register
- SON INFRA ENTERPRISES
- Projects on the register
- 1
- Registering since
- 2026
- Complaints on the promoter
- 0, as shown on this registration
Aavya Homes: questions answered
Where is Aavya Homes located?
The Karnataka RERA register places Aavya Homes in Anekal, Bengaluru Urban.
What is the RERA number of Aavya Homes?
The Karnataka RERA registration number of Aavya Homes is PRM/KA/RERA/1251/308/PR/200126/008411, approved on 20 Jan 2026.
Who is the promoter of Aavya Homes?
The promoter filed on the Karnataka RERA register is SON INFRA ENTERPRISES.
When is Aavya Homes expected to be completed?
The proposed completion date filed on the register is 31 Dec 2028.
How big is Aavya Homes?
The register lists Aavya Homes with 80 units, 1 tower and about 0.73 acres of land.
What is the latest construction progress of Aavya Homes?
The quarterly report for Q4 2025-26, filed on 15 Jul 2026, shows construction 70% complete and 6 of 80 units booked.
Where does this information about Aavya Homes come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.